  • Develog: Early July, 2011

    • Renderer:
      • Programming interface: done, for now
      • Error handling: done, for now
      • Documentation: ongoing
      • Perspective projection: to-do, due 14/7
      • Lighting: to-do, basic functionality due 20/7
      • Texturing: to-do
    • Game Logic:
      • Exit: done, for now
      • Everything else: to-do
    • Network:
      • Everything: to-do
    • Modelling:
      • Everything: to-do
    • Physics:
      • Everything: to-do
    • Sound:
      • Everything: currently not on schedule
    • Optimisation:
      • Everything: currently not on schedule
    • Debug:
      • For all components: never ends